SR-350 Road Improvement Project
Full Depth Reclamation (FDR) Production Schedule Notice
Dear Residents, Community Members, Businesses, and Emergency Personnel,
As part of the ongoing SR. 350 Road Improvement Project, Full Depth Reclamation (FDR) production is tentatively scheduled to begin Thursday, July 9, 2026, and continue over an 11-day production schedule, weather permitting. Work will generally occur Monday through Saturday, with no production on Sundays.
Expected Work Hours
6:00 AM – 6:00 PM, weather permitting
During active construction, crews will reclaim and stabilize the existing roadway to create a stronger foundation for the new pavement. While every effort will be made to maintain local access, there may be periods when access to homes, businesses, and side roads is temporarily limited while crews are working directly in front of those locations.
What to Expect
Lane restrictions/ through traffic closure and reduced speeds
Rough roadway conditions within the active work zone
Construction equipment, dust, and noise
Temporary delays entering or exiting driveways
“No Through Traffic” signage and barriers closing off active construction zones
Essential Services
Access will be maintained as practical for:
Emergency services
Mail delivery
Trash collection
Local residents and businesses
Tentative Production Schedule
Please note: The schedule below is subject to change due to weather, equipment, or field conditions. Residents should expect work to reach their property within approximately ±1 day of the dates shown.
Production Day | Date | Addresses / Roads Affected |
Day 1 | July 9, 2026 | 8137 Sr. 350 -8053 Sr. 350 |
Day 2 | July 10, 2026 | 8001 Sr. 350 -Clark Rd. |
Day 3 | July 11, 2026 | Clark Rd.-7471 Sr. 350 |
Sunday | July 12, 2026 | No Production |
Day 4 | July 13, 2026 | 7181 Sr. 350 -6843 Sr. 350 |
Day 5 | July 14, 2026 | 6843 Sr. 350 -6540 Sr. 350 |
Day 6 | July 15, 2026 | 6275 Sr. 350 -Farmers Rd. |
Day 7 | July 16, 2026 | Farmers Rd.-5635 |
Day 8 | July 17, 2026 | 5635 Sr. 350 -5388 Sr. 350 |
Day 9 | July 18, 2026 | 5388 Sr. 350 -4852 Sr. 350 |
Sunday | July 19, 2026 | No production |
Day 10 | July 20, 2026 | 4852 Sr. 350 -4415 Sr. 350 |
Day 11 | July 21, 2026 | 4415 Sr. 350 – Sr. 134 |
We appreciate your patience and cooperation as we complete these important improvements to SR 350. Please use caution when traveling through the work zone, obey all posted signs, and watch for construction personnel and equipment.
Project Contacts
Brian Stephens
ODOT Inspector
(513) 218-7860
Rylee Ankeney
Assistant Project Manager
John R. Jurgensen Company
(513) 619-0546