SR-350 Update 8



SR-350 Road Improvement Project


Full Depth Reclamation (FDR) Production Schedule Notice


Dear Residents, Community Members, Businesses, and Emergency Personnel,


As part of the ongoing SR. 350 Road Improvement Project, Full Depth Reclamation (FDR) production is tentatively scheduled to begin Thursday, July 9, 2026, and continue over an 11-day production schedule, weather permitting. Work will generally occur Monday through Saturday, with no production on Sundays.


Expected Work Hours

  • 6:00 AM – 6:00 PM, weather permitting


During active construction, crews will reclaim and stabilize the existing roadway to create a stronger foundation for the new pavement. While every effort will be made to maintain local access, there may be periods when access to homes, businesses, and side roads is temporarily limited while crews are working directly in front of those locations.


What to Expect

  • Lane restrictions/ through traffic closure and reduced speeds

  • Rough roadway conditions within the active work zone

  • Construction equipment, dust, and noise

  • Temporary delays entering or exiting driveways

  • “No Through Traffic” signage and barriers closing off active construction zones  


Essential Services

Access will be maintained as practical for:

  • Emergency services

  • Mail delivery

  • Trash collection

  • Local residents and businesses


Tentative Production Schedule

Please note: The schedule below is subject to change due to weather, equipment, or field conditions. Residents should expect work to reach their property within approximately ±1 day of the dates shown.


Production Day

Date

Addresses / Roads Affected

Day 1

July 9, 2026

8137 Sr. 350 -8053 Sr. 350

Day 2

July 10, 2026

8001 Sr. 350 -Clark Rd.

Day 3

July 11, 2026

Clark Rd.-7471 Sr. 350

Sunday

July 12, 2026

No Production

Day 4

July 13, 2026

7181 Sr. 350 -6843 Sr. 350

Day 5

July 14, 2026

6843 Sr. 350 -6540 Sr. 350

Day 6

July 15, 2026

6275 Sr. 350 -Farmers Rd.

Day 7

July 16, 2026

Farmers Rd.-5635

Day 8

July 17, 2026

5635 Sr. 350 -5388 Sr. 350

Day 9

July 18, 2026

5388 Sr. 350 -4852 Sr. 350

Sunday

July 19, 2026

No production

Day 10

July 20, 2026

4852 Sr. 350 -4415 Sr. 350

Day 11

July 21, 2026

4415 Sr. 350 – Sr. 134


We appreciate your patience and cooperation as we complete these important improvements to SR 350. Please use caution when traveling through the work zone, obey all posted signs, and watch for construction personnel and equipment.

Project Contacts


Brian Stephens

ODOT Inspector

(513) 218-7860


Rylee Ankeney

Assistant Project Manager

John R. Jurgensen Company

(513) 619-0546

 
 
 

Comments

Rated 0 out of 5 stars.
No ratings yet

Add a rating
bottom of page